Management and Contracting Arrangements
A. Implementing Agencies and Australian Contractor
Implementing Agency
Australian Agency for International Development (AusAID)
Australian Managing Contractor (AMC)
SMEC International Pty Ltd (SMEC), in association with Intelligent Energy Systems (IES) and the Australian Bureau of Agriculture and Resource Economics (ABARE).
Partner Countries
Indonesia, Malaysia, Philippines, Thailand and Vietnam
ASEAN partner organisations
ASEAN Center of Energy (ACE)
ASEAN Secretariat
B. Background
The project has had a long period of gestation. It was initially developed to Draft Project Design Document stage by a feasibility design study team in 1995. Due to budget uncertainties in Australia, authorisation was not finally received until October 1996. With the passing of time and because various aspects of the project needed to be clarified, a revision team was fielded in 1997 to finalise the design of the project. The revision mission visited the Philippines, Malaysia and Thailand in May 1997, Indonesia in June 1997 (during which the ASEAN Secretariat was further consulted) and Vietnam in July 1997.
This project commenced in March 1999 when AusAID entered into a contract with an Australian Managing Contractor (AMC) to deliver the project. Due to changes within the AMC brought about by a subsequent takeover in the latter half of 1999, AusAID concluded in June 2000 that the AMC was unable to provide staff and other resources of the appropriate standard and quality. As a result, the project entered a period of suspension while AusAID conducted a Stocktake Mission to the participating countries in October/November 2000 to assess project progress and to report on changes to project design to be included in any re-commencement of project activities.
The project was re-tendered in 2001 and the contract with the new AMC was signed on 22 February 2002, which defined the formal date of project commencement. With a four-year duration, the formal project completion date was 31 March 2006.
The new AMC was SMEC International Pty Limited, with Intelligent Energy Systems (IES) and ABARE assisting as sub-contractors.
A chart indicating the organisation arrangements for the project is shown as Figure 1.1.
Figure 1.1 : EPSAP Organisation Chart
 |